Tailings stacking · Australia + global projectsVisit Kontain
DRY STACKED
TAILINGSA KONTAIN TECHNICAL RESOURCE

Featured technical article · Kontain perspective

Why smaller mines should reconsider geobag tailings storage

For mines producing 100,000 to 1 million dry tonnes of tailings a year: operating costs, upfront capital and conservative site allowances.

A geobag priced at A$7 per dry tonne buys more than a consumable. It provides a dewatering container that retains solids in their final storage position, suppresses dust from the enclosed material and reduces its direct exposure to rainfall. For a smaller mine, combining these functions can make geobags a highly competitive tailings-management option.

The comparison becomes particularly compelling when the alternative includes a filtration plant followed by cake transport, conditioning, placement and compaction. Our illustrative geobag subtotal is A$10.60/dmt, including selected operating costs and additional footprint and standby-pad allowances. Filtration and placement total A$10/dmt before plant capital; an illustrative A$20 million plant adds A$2/dmt at 500,000 dmt/year over 20 years. The remaining infrastructure and operating costs still need to be reconciled, but the case for a serious comparison is already clear.

Kontain supplies geobags, and this is our commercial and technical perspective. We recommend that mines producing 100,000 to one million dry metric tonnes of tailings a year include permanent geobag storage in their options assessment. The technology offers a practical way to dewater, contain and progressively store suitable tailings without creating a separate cake-handling operation.

Include the work after filtration

A useful comparison follows the same incoming tailings stream through to its final stored condition. A filtration-only operating rate stops too early. The filter produces cake; the project must still get that cake into an appropriately formed and managed stack.

Published research recognises this distinction. Carneiro and Fourie's Western Australian conceptual study included transport, spreading, moisture conditioning and compaction. It used a placement rate of A$3.65/t for a hypothetical 2 Mtpa operation with a 1 km haul. Annual maintenance, labour and administration were excluded on an assumed-similar basis. The lesson is to examine what a quoted rate includes, rather than assume every published total covers the same work. [1]

SRK describes fully compacted dewatered stacks as continuing earthmoving operations whose operating costs can exceed those of the dewatering plant. Its discussion also shows how structural and non-structural zones can change the required compaction effort. The placement allowance should follow the proposed deposition design. [2]

Geobags installed in their permanent position combine dewatering and deposition. Solids accumulate inside the unit while water drains out; separate transport and compaction of filter cake are avoided. That benefit belongs in the comparison alongside the bag purchase. Temporary dewatering followed by excavation or relocation is a different arrangement and should include its subsequent handling costs. [3, 7]

A competitive operating comparison

The following Australian-dollar example excludes GST. The bag inputs are Kontain's budgeting allowances for suitable heavy tailings. Bag purchase prices increase with unit size, so the A$7/dmt supply allowance stays constant across the selected payload range. Filtration at A$4/dmt and placement at A$6/dmt are editable comparison inputs.

Selected operating costGeobag storageMechanically filtered stack
Bag supply per dry tonne storedA$7.00/dmt—
Bag deployment and connectionsA$2.50/dmt—
Pumping and dosing electricityA$0.30/dmtIncluded in filtration
Routine equipment servicing, minor parts and maintenance labourA$0.20/dmtIncluded in filtration
Filtration including process power, operators and routine maintenance—A$4.00/dmt
Loading, transport, conditioning, spreading and compaction as required—A$6.00/dmt
Selected operating subtotalA$10.00/dmtA$10.00/dmt

The A$0.50/dmt combined geobag electricity and maintenance provision is a manual budgeting allowance, rather than a published industry benchmark. Pumping duty, pipeline length, slurry abrasion and operating hours determine the site allowance. At 500,000 dmt/year it represents A$250,000 annually.

These are selected operating subtotals. Bag filling and dosing supervision, excavator use and other water-management support must be included wherever they are additional. Capital, storage infrastructure, polymer and closure are assessed separately. Filtration power, operators and routine maintenance are already inside the filtration allowance and must not be counted again. Placement contractor or hire rates may also recover equipment capital; check their scope before adding loaders, trucks or conveyors as separate capital.

On operating costs alone, the mechanical placement break-even is A$6.00/dmt: A$10.00 for bags less A$4.00 for filtration. The conservative additional bag-site allowances below increase it to A$6.60/dmt before other capital differences. The tool shows both the operating comparison and the comparison including entered site and capital allowances.

The historical A$3.65/t placement assumption, if treated as a 2018 dry-tonne rate, becomes approximately A$4.83–5.00/dmt when indexed to September 2026 using the ABS Other Heavy and Civil Engineering Construction series. This is useful cost context rather than a contractor quotation: the original rate's precise price base and dry-tonne interpretation are assumptions in that escalation. [1, 4]

A relevant throughput reference is WSP's 2026 Peruvian study. Its first stage processes 1,500 dmt/day for 360 days, approximately 540,000 dmt/year. Filtration operating cost is US$2.51/t, including electricity, operating personnel and maintenance. Loading and an 8.6 km truck haul add US$4.75/t, giving a reported subtotal of US$7.26/t. Initial filtration-plant capital is separately estimated at US$20.79 million. [5]

These are Peruvian estimates in US dollars, with a substantial haul distance. They demonstrate why a filtration operating rate alone cannot represent the complete system cost. The loading-and-haul increment should not be assumed to include every subsequent conditioning and compaction activity. Our A$20 million capital example below is a separate assumption, not a currency conversion of WSP's estimate.

Labour should follow the work

Geobag deployment and connections are periodic tasks. A shared site crew can install the next units, connect lines and return to other work between activities. Filling management and inspections remain part of the operating plan. Mechanical systems likewise require operators and maintenance support, plus the people and equipment involved in their placement route.

The calculator allows either measured deployment hours or a manual A$2.50/dmt allowance. For context, four people at A$100 per person-hour working eight hours on a 1,000-dmt bag cost A$3.20/dmt before equipment. The A$2.50 allowance corresponds to 6.25 crew-clock hours at that rate and payload. Actual bag size, deployment time and shared duties determine the appropriate input.

At 2,000 dmt per bag, 100,000 dmt/year requires about 50 units annually, or approximately one per week. At 600,000 dmt/year, it requires about 300 units annually, or six per week. This is a manageable planning basis for scheduling deployment, filling and drainage within an engineered pad layout. Bag supply remains A$7/dmt in the example as the unit price scales with capacity.

Allow for the footprint and a practical standby pad

The comparison starts with matched concept designs for site preparation, lining, drainage, water management and closure. For conservative early planning, Kontain suggests testing a geobag footprint 20% larger than the equivalent exposed stack. This allows for a potentially flatter bag-stack geometry and operating layout. Actual footprints may be similar, or the difference may be larger; the geometry, density, access and foundations determine the result.

Our worked example carries two additional geobag construction allowances, allocated across project dry tonnes:

Additional geobag site allowanceIllustrative allocation
Additional civils and lining associated with footprintA$0.50/dmt
Separate standby deposition pad for approximately one month of productionA$0.10/dmt
Additional site allowanceA$0.60/dmt
Selected operating costs plus these additional site allowancesA$10.60/dmt

The A$0.50/dmt is a manual comparison allowance. It equals a 20% increase only where the relevant base civils-and-lining cost is A$2.50/dmt. The calculator also offers a percentage-based option using the entered baseline. Apply one approach, and do not add the premium again where the full bag-pad estimate already includes the larger footprint. These are allocated construction costs, not recurring operating expenses.

We suggest reserving a separate standby deposition pad for approximately one month of production so deposition can continue during bag replacement, a local filling incident or planned stack maintenance. At 500,000 dmt/year, this is approximately 41,667 dry tonnes of standby capacity. At an assumed 1.4 dmt/m³, it represents about 29,762 m³ of settled material; incoming slurry, drainage, bags and operating access require their own design allowances.

The A$0.10/dmt is an editable construction-budget assumption, not a maximum price. Over a 20-year, 500,000 dmt/year project it represents A$1 million. Standby deposition capacity is separate from emergency spill containment and stormwater storage. Spare bags, incident clean-up and any extra operating support are costed separately unless included in the project estimate.

Unitised storage and reduced mobile-water inventory can support more localised containment arrangements and potentially smaller bunds. Bund dimensions still follow credible release volumes, stormwater, foundation conditions and whole-stack stability. The comparison allows this benefit to be assessed through the actual design, rather than applying a universal bund reduction.

Common upstream polymer and infrastructure costs remain in both routes, with any genuine difference identified separately. This keeps the focus on what each option actually requires to deliver the final stored tonne.

The filtration plant must be funded upfront

A filtration operating rate does not recover an owned plant's initial capital unless the rate explicitly includes it. Consider an illustrative A$20 million fully installed filtration plant serving a mine producing 500,000 dry tonnes of tailings annually. Allocating that investment across the production schedule gives:

Operating periodTotal tailings processedInitial filtration capital per dry tonne
5 years2.5 million dmtA$8.00/dmt
10 years5 million dmtA$4.00/dmt
15 years7.5 million dmtA$2.67/dmt
20 years10 million dmtA$2.00/dmt

This simple allocation assumes the stated annual production is achieved. It excludes financing, the time value of money, subsequent capital renewals and residual value. The installed filtration-plant allowance is separate from storage pads and other shared infrastructure.

Twenty years is a reasonable assessment scenario where the mine plan supports it. A published tailings-dewatering lifecycle comparison uses a 20-year operating period; that is a modelling assumption, not a universal equipment lifespan. WSP's example plans five years at initial capacity followed by 15 years at expanded capacity. Component renewals and major refurbishments belong in maintenance or sustaining capital as appropriate, counted once. [5, 11]

Under the 20-year illustration, mechanical filtration and placement total A$12.00/dmt including initial filtration-plant capital. Over ten years, they total A$14.00/dmt. In the 20-year illustration, the geobag selected operating and additional site allowances total A$10.60/dmt, before remaining pumping and dosing capital and other unmatched costs. For shorter projects, reallocate each option’s fixed capital and pad costs across the actual tonnes. The A$1.40/dmt difference in the 20-year example is available to absorb those remaining differences; a project saving is established after they are reconciled.

The placement break-even follows the same scope. Including the A$0.60/dmt additional bag-site allowances, it is A$6.60/dmt before other capital. With A$2.00/dmt filtration-plant capital, it becomes A$4.60/dmt plus the bag system's other capital allocation per dry tonne. Any remaining unmatched operating or infrastructure difference also belongs in that calculation.

For smaller mines, cash timing matters as well as the average rate. The filtration investment is committed before production, while bag purchases can follow the tonnes produced. Pumps, dosing equipment and pads still need funding, but the storage inventory can grow progressively with the operation. This combination of competitive selected costs and a lower initial mechanical investment is a strong reason to assess geobags early.

Use the project's supported production schedule. A plant capable of operating for 20 years does not justify a 20-year cost divisor where the mine only supports ten. Wet-storage stages, plant expansions, replacement equipment and residual value should all follow their actual timing in the full-project comparison.

Wet storage has a substantial construction cost

A TSF raise benefits from an existing facility; a new storage development may need foundations, roads, drainage and water infrastructure from the outset. Divide each cost by the usable dry capacity that expenditure creates. Annual mine production and storage volume in cubic metres are different denominators.

For a published Australian example, Aeris reported A$17.3 million for a Cracow TSF upgrade adding approximately one million cubic metres and around three years of production capacity. That is A$17.30/m³. At an assumed dry density of 1.4 dmt/m³, the equivalent is A$12.36/dmt of added capacity; a project-specific dry density is required for the conversion. This was an expansion, not a new facility. [6]

Kontain's discussions with mine operators also include stage allowances around A$10–15/dmt and markedly higher new-facility costs. Two confidential Australian examples were reported at approximately A$45 million for two million dmt and A$30 million for one million dmt: A$22.50/dmt and A$30/dmt respectively. These are operator-reported cost-and-capacity pairs, retained anonymously as project context rather than published market benchmarks.

Construction cost is only one part of wet storage. Deposition, water return, monitoring, maintenance and closure also belong in the whole-life estimate. At the same time, published studies contain lower-cost wet-storage options. The commercial case for bags is strongest when it is established from the site's actual alternatives, rather than a universal dam rate.

Operational benefits beyond the rate per tonne

Geobags offer a simpler process at the storage location. Pumping and filling pressure initiate drainage, followed by continued water release and consolidation under gravity, self-weight and subsequent loading. Each bag performs its dewatering function without a continuously operating mechanical press. This reduces the mechanical equipment associated with the dewatering step, while pumping and dosing duties remain straightforward items to cost. [3, 7]

Enclosing the tailings suppresses dust from the stored fines and avoids dust-generating cake transfer and placement activities where the bags remain in position. The fabric provides continuing surface containment as the material dries. Normal road, spill and later excavation controls still apply, but the exposed tailings surface is fundamentally different from an open stack. [8]

Bag geometry and surface containment also reduce direct rainfall exposure and can limit rewetting compared with loose, exposed material. Rain sheds from the curved surface, while the contained solids retain their position. The fabric is permeable, so this advantage works with a graded pad and effective drainage; it is not a waterproof barrier. Australian geotextile-tube experience reports reduced direct rewetting, supporting this practical benefit. [9]

An exposed filtered stack must accommodate rainfall, changing moisture and trafficability through its deposition and stormwater design. Depending on the material and climate, this can involve conditioning, working-area management and compaction. Some designs use uncompacted zones, so the allowance should follow the design rather than a blanket rule. [10]

For future reuse, identifiable bag cells can keep dewatered material accessible and segregated. That can support recovery planning without relying on an active wet impoundment. Opening bags, removing fabric and any subsequent processing are then costed as part of the recovery operation.

Manage risk through controlled filling and smaller inventories

Geobags change the form and distribution of the stored material. Dewatering reduces mobile water, while separate units divide the incoming slurry inventory into smaller compartments. This is an important distinction from retaining a large connected inventory of water and wet tailings. It gives designers a more localised initial loss-of-containment scenario to manage.

During filling, the operating procedure sets maximum fill height and pressure, controlled flow and clear stop criteria. The system design can specify overflow, pressure-relief or automatic shutdown arrangements to provide further protection. These are practical safeguards against overfilling, supported by inspection of connections, fabric and seams. Overfilling is an operating condition to control, not an inherent reason to reject the method. [3]

As drainage and consolidation progress, the material becomes less mobile and behaves increasingly as a contained soil mass rather than pumped slurry. A fabric defect in a consolidated unit is therefore a different event from a failure during filling. The design still considers erosion, local release and interaction between units; neither the likelihood nor the consequences of every possible event can be reduced to a single bag without considering the stack as a whole. [7]

Foundation performance, overall stability, drainage and closure remain normal engineering responsibilities. The advantage is a storage arrangement with reduced mobile-water inventory and defined operating units, rather than a claim of zero risk. That provides a sound basis for comparing consequence, inspection and maintenance requirements alongside cost.

Work through the comparison with Kontain

For suitable tailings at smaller mines, geobags can combine competitive cost with simpler dewatering, less handling, dust suppression and progressive expenditure. The worked example remains competitive even after explicit electricity, maintenance, footprint and standby-pad allowances. Regulators, designers and operators should give this option meaningful consideration alongside wet storage and mechanically filtered stacks. Their value becomes clear when the comparison includes the work required to deliver the final stored material, rather than stopping at the outlet of a filter.

Kontain's Tailings Cost Comparison tool is free to use through our website. We strongly recommend a presentation and a guided comparison with Kontain before relying on the results for a project decision. The calculation is straightforward; choosing consistent payload, labour, plant, placement and storage inputs requires knowledge of the proposed operation.

We can work with the mine's technical and operating teams to establish those inputs, compare the complete alternatives and identify the site information needed for a useful estimate. The tool remains freely available for users who already understand their inputs and want to explore their own scenarios.

Use the free calculator on the Kontain website: https://kontainsolutions.com/tailings-cost-comparison/

Explore the geobag design tools for layout and capacity planning: https://kontainsolutions.com/design-tools/geobag-design-tools

Arrange a presentation and guided project comparison with Kontain: https://kontainsolutions.com/request-quote

Sources and calculation basis

[1] Carneiro A and Fourie AB 2018. A conceptual cost comparison of alternative tailings disposal strategies in Western Australia. Paste 2018, pp. 442, 446–447 and 451. https://papers.acg.uwa.edu.au/d/1805_36_Carneiro/36_Carneiro.pdf

[2] Norambuena Mardones RE, Caldwell-Crystal C and Cobos D 2023. How high is too high? Challenges on the next generation of dewatered tailings stacks. Paste 2023, pp. 468–469. https://papers.acg.uwa.edu.au/d/2355_35_Norambuena/35_Norambuena.pdf

[3] Assinder PJ, Breytenbach M, Wiemers J and Hörtkorn F. Utilizing geotextile tubes to extend the life of a Tailings Storage Facility. HUESKER and SRK, sections 4.2 and 5. https://www.huesker.com.au/fileadmin/media/Scientific_Revised_Paper/P761_Utilizing_geotextile_tubes_to_extend_the_life_of_a_Tailings_Storage_Facility_.pdf

[4] Australian Bureau of Statistics. Producer Price Indexes Australia September 2026, Table 17, series A85220823L. The escalation assumes a 2018 price base and dry-tonne interpretation. https://www.abs.gov.au/statistics/economy/price-indexes-and-inflation/producer-price-indexes-australia/sep-2026/6427017.xlsx

[5] Gonzales G and Huillca G 2026. Detailed engineering for the implementation of filtered tailings in Peruvian underground mining. WSP, Paste 2026, pp. 9–10. Costs retained in US dollars. https://papers.acg.uwa.edu.au/d/2655_13_Gonzales/13_Gonzales.pdf

[6] Aeris Resources 2024. Annual Report, pp. 2 and 10. https://aerisresources.com.au/wp-content/uploads/2024/10/Aeris_AR_2024_WEB.pdf

[7] da Silva F 2023. Stacked deposits of thickened and filtered fluid fine tailings using geotextile tubes concepts and lessons learned updates. Paste 2023, pp. 640–645 and 649. https://papers.acg.uwa.edu.au/d/2355_49_da_Silva/49_da_Silva.pdf

[8] Solmax. GEOTUBE Dewatering for Mining and Mineral Processing, APAC brochure, p. 5. https://geofabrics.co/sites/default/files/2024-07/GEOTUBE_Dewatering_for_mining_and_mineral_processing_APAC_1123_Web(1).pdf

[9] Smith M 2009. Geotextile tubes in environmental applications. Australian Geomechanics Society Sydney Chapter Symposium, pp. 110 and 119. https://geomechanics.org.au/wp-content/uploads/2023/04/K-Smith-paper.pdf

[10] BHP and Rio Tinto Tailings Management Consortium 2026. Unlocking Large Tonnage Filtered Tailings Stacks A Geotechnical Perspective, March, pp. 12 and 24. https://www.bhp.com/-/media/project/bhp1ip/bhp-com-en/documents/sustainability/tailings-storage-facilities/260508_whitepaperfilteredstacks.pdf

[11] Chinchankar AP 2024. Lifecycle cost comparison: modern solid-bowl centrifuge technology outperforms filtration in tailings dewatering. Paste 2024, pp. 27–38. Supplier-authored comparison using a 20-year assessment period; cited for that modelling basis only. https://papers.acg.uwa.edu.au/p/2455_01_Chinchankar/

Take the next step

A project comparison, with the right inputs.

Bring your mine’s production basis and existing quotations. We can walk your team through the options.